Category: Procurement & Contracts

Observation

Our website has several articles on  “observation”.  When claims are based on building failures, inevitably the role of observation comes under scrutiny.  This article is the combination of thoughts from four NZACS Directors:  Peter Marshall, Alec Couchman, Michael Davis, and Colin Orchiston.

Observation versus Contract Administration

The current standard forms of engagement and contract intermingle observation with contract administration, and whilst they are interdependent, they are also separate.  This separation of roles is likely to increase, and the NZIA is actively involved in current MBIE consultations around establishing the contract administration role as a stand-alone.

If you are engaged for observation you can report on what you have observed, but the duty to administer the contract – including ruling on variations, certifying payments and completion – rests with the contract administrator. 

A consequence of separating the roles might be that rectification needed as a result of the observation role cannot be enforced because the leverage obtainable by with-holding payments is at the discretion of the separate contract administrator.

The role of Observation by the Architect primarily arises out of the terms of engagement between the Principal and the Architect.  The role of Contract Administration arises out of the (building) contract between the Principal and the Contractor.  If a building contract provides for independent observation (as does NZIA SCC at 8.8 and NZS3910 at 6.4) then those terms will provide the scope and rights/obligations applicable.  If the building contract does not provide for independent contract administration or observation, and/or is inconsistent with the architect’s terms of engagement, the scope and terms will need to be agreed elsewhere, failing which they will be uncertain.

In a larger practice, the roles of designer, contract administrator and observation can be parcelled out to different staff, and the bigger projects suggest repetition of some site activities;  when the same person does all three roles, the familiarity with the project suggests that critical aspects for observation should be known.

Partial Observation is a high-risk option

Any hint that the terms of engagement include observation will lead to assertions that building failures are the result of the architect failing to correct the work at the time it was done. 

This makes the provision of “partial services” or “limited observation” or “site attendance on request only” or some fixed (eg weekly or monthly) site visit frequency a risky proposition which should be resisted.  These arrangements may remove or diminish your control over the sufficiency of your observation, and yet you may still be held responsible for the full weight of “proper” observation. 

It would be nice to just say “don’t do it” but the reality in the market is that it is necessary to view it as an unwelcome option that requires careful risk management. 

  • Who is to say what you could or should have seen when you went on site? 
  • Or whether you were on site sufficiently? 
  • Or for the right reasons or at a critical point in time? 

Our website has several articles on “Partial Services” and they are not the focus of this article, but it is difficult to defend an allegation of inadequate observation on the basis that only “limited” oversight was intended, or was possible. 

One of the early WHRS claims considered the defence offered by a Building Inspector that he was over-worked and the available resources provided by his employer meant that he could not adequately carry out the level of inspection necessary:  unsurprisingly the Court took the view that the regulatory duties were not diminished because of management failures by the provider! 

Against that background, there has to be a very thorough defence to justify why an architect engaged for observation did not – or could not –instruct rectification of observably defective work.

The Observation role should be whole-hearted, with attendances as and when required, with fair and commensurate fees, and with scope and fees sufficiently flexible to deal with changes in the circumstances of the project. 

How much is “enough”?

The Project Architect should assess the level of observation and the frequency of site visits at time of agreeing the terms of engagement.  It is (possibly) more important to set out what you won’t do, than to say what you will do;  and essential to provide for changes to reflect the changing circumstances of the project.  The architect’s risks are compounded if the level of observation as agreed in the original terms of engagement does not correlate with the level of observation later required or sought. 

In smaller projects this may arise because the client removes observation and contract administration from the architect’s scope during the procurement process. 

In larger projects it would not be unusual for the architect to be appointed early in the process and then later a project manager arrives who then appoints and instructs the consultants;  the architect is removed from the contractor procurement process;  contract administration is undertaken by others;  the architect’s role is limited to clarifying the documentation and restricted site access for monthly reporting;  the consultants remain responsible for observation but do not have the power to obtain rectification;  yet on completion the funding agencies look to the architect to certify completion.

Engineers have a structured approach to determining the level of observation and frequency, but it does not take into account the issues we face as architects carrying out observation.  It is not really about how often one visits the site, but whether the site visits capture the critical issues:  that suggests that the project architect should be keeping an eye on the site progress, identifying what issues are likely to be critical if not performed as required, and planning site visits around those issues.  Subject to ongoing review, an initial assessment might be on the following basis:

OL1        Intermittent Site Visits:  small & simple projects                 fortnightly visit

OL2        Periodic Site Visits:          medium complexity & size           weekly visit

OL3        Regular Site Visits:           larger or more complex                 twice weekly visit

OL4        Constant Site Visits:        major complexity and scale          every second day

This may or may not suit the project, the potential risk, or the fee, and is complicated by:

  • Construction activity varying over the duration of the project, from site mobilisation and excavation through to a myriad of trades finishing works.
  • The skills and experience of the contractors and sub-contractors, which may require more observation to mitigate risk.
  • Progress on site varying from programme or expectations.
  • Sufficiency accuracy and reliability of design and as-built documentation, and the level of co-ordination between consultants, may lead to more on-site queries and site visits.
  • Substitutions or redesign sought by contractors;  client and/or project manager changes, demands, expectations;  similarly, from incoming occupants/owners and their funders, and overlaps with fitout requirements.
  • Critical technical and programme issues, specific design complexities, perhaps where the risk of non-compliance varies disproportionally in relation to cost, scale and complexity.
  • The need to exhibit to the contractor and client that you are “on top of things”
  • The number of site visits not reflecting the duration of the visit, eg 1 hour; 3 hours, etc.

There is also a “bell-curve” which is typical:  for smaller projects especially, a lot of attendance is necessary at the start of the job while the builder is grappling with what is required (and the architect is gauging how much hand-holding or vigilance may be required);  in the middle of the project when there is a lot of repetitive work the only reason to visit might be for the purpose of valuing a progress claim;  at the closing stages monitoring of finishing items may be to the level necessary to keep the client happy.

Observation does not mean inspection, or supervision

Lawyers and the courts do not appear to recognize the fine hair-splitting implied in this statement, and lawyers seemingly make no distinction between undertaking one site visit a month as opposed to a permanent site presence when it comes to blame.  But that doesn’t make the distinction incorrect.  It suggests that we need to do more to communicate the distinction. 

Supervision is the control and direction of the work;  Observation is a review of the work done. 

Observation of a typical installation versus every installation

We are judged against what is deemed to be the actions of a reasonable architect in those circumstances at that time.

If you observe a representative quantum of a particular aspect of work to confirm that it matches your documentation and make the assumption on reasonable grounds that the remainder of that work will be similar, those are the actions of a reasonable architect.  If a client wants more than that they need a clerk of works, and even then there’s no guarantee of perfection.

It is reasonable – in absence of evidence to the contrary – that an Architect assume that the contractor is competent:  if a typical item of work is acceptable, and there was nothing to suggest that the remainder of that type of work would be executed any differently, then those other instances of that work may be assumed to also be acceptable.   

But if a window is leaking because of an obvious and observable fault, and the architect did not notice the poor installation when there was the opportunity and need to do so, then they will be dragged into the issue, regardless.  To claim that inspecting one window is sufficient for all windows would be a weak defence if 90% of the windows subsequently leaked (even if the one window the architect did inspect was perfect). 

If you review an item of construction in detail and it is aligned with the documentation and complies with NZBC you can accept it, but you cannot then step back and not carry out observation of those repeating elements.  At the very least you would need to review the repeated elements to the extent necessary to conclude that they were consistent with the item reviewed in detail.  If the review of several such items revealed a variation in installation quality, the conclusion would be that site quality control is lacking, and more follow-up is required. 

The question is whether what was observed was representative of that part of the construction:  inspecting a window “type A” may or may not inform about the installation of types B,C etc.  If there are 100 similar items then a reasonable assessment has to be made whether to observe in detail 1,10, or any number of them to be satisfied that the work is being done as required.  Were they installed by the same persons at a similar point in time?  By skilled or unskilled staff?  What quality controls were in place?  What are the consequences of failure?  Who is likely to respond – and how – in the event of failure?  For marginally acceptable items, how does the installed item compare to independent benchmarks or to supplier’s requirements?

Be very wary of providing any sort of statement as to quality/completion/compliance

Your observation role is to report on whether the work done complies with the contract requirements;  your reporting can only be on the basis of what you have seen, and what you can reasonably infer from what you have seen.  Your reporting will be dependent on the conditions under which the observation took place:  the weather, the available access, whether the item was complete or in progress, and what information was provided to you by those on site who directed the work.  If your reporting is based on assumptions, make those assumptions known. 

Your observation reports will be used for two purposes:  to inform the contract administrator about the progress and compliance with the contract requirements, and to provide ammunition to those who want to pin liability on you for subsequent shortcomings.

Covid or Supply-Chain Costs and Delays

Most of us will be aware of the problems builders are having in getting materials onto sites at reasonable times and costs.  This will have a consequential risk for design practices:  your Risk Management should be looking beyond the short term and thinking about the effect that these problems will have in the future.

If you had any doubt about the seriousness of these issues, take a look here:  https://www.eboss.co.nz/supply-chain-report-2021/background

https://www.corelogic.co.nz/news/construction-costs-rise-22-three-months-june-fastest-quarterly-growth-record#.YTASCo4vNPZ

These delays and costs have the potential to create problems, particularly in claims for fluctuations or cost increase claims, and extension of time claims.  We urge members to keep clients informed, and to encourage contractors to be open and transparent.  Good-faith negotiation should always be undertaken ahead of escalating competing views to the level of a dispute.  Whilst the contract terms may or may not “properly” allow for the contractor to recover the time or cost consequences of the current difficulties, the parties to a contract can always agree to a change in the contract terms, or one party can unilaterally waive some rights (for example, liquidated damages). 

Where such changes are contemplated, be sure to document them clearly and specifically, so that they do not create more problems than the original situation.  The beneficiary of the changes should be the project, not one or more of its participants.

These issues will impact on client/designer/builder/funder relationships.  The material cost changes of 5% to 25% in the past year or so are the harbinger of more upward movement.  Labour costs are being driven up by tight labour resources and contractors well booked into the future.  The supply chain problems are disrupting site progress, leading to project delays and pressure on contractors’ margins. 

The problems are not ours alone:  America and Europe are also troubled by shortages of materials and labour, slow and expensive shipping and varying lockdown measures.  Covid is driving up inflation generally, and the size of our economy (and construction industry) means we have ineffective leverage on material supplies.

Clients with projects at design stage may be unable to accommodate these costs and delays within their budgets.  Others will continue but with resentment adding stress to the project.  Still others will be looking to continue but with cost cuts which may compromise the design and add to design costs.  Procurement strategies may favour early contractor design involvement, movement away from lump sum contracts to an arrangement which redistributes the risk of delays and cost increases, staged consenting and contracting, and design-stage identification and ordering of items requiring long lead times.

Projects under construction will come under stress if builders cannot complete within the time and cost parameters understood when the project was priced.  If increased costs cannot be recovered, performance on site is at risk or perhaps may be abandoned.  Where costs can be recovered, they will not be welcomed by clients.  Arguments from delays beyond those directly related to Covid lockdowns will be unpleasant.  All of those circumstances represent increased risk to you:  both additional (and perhaps unrecoverable) attendances, and the potential for dispute and negligence claims.

In order to manage those risks, please take the time to assess how these issues will affect all the projects you have underway, in particular where reliance has been placed on pre-Covid cost/time estimates, and to communicate appropriately with each client. 

Contract Administration versus Contract Management

Members will be aware of assertions that architects show bias in contract administration, and are not up to the task.  A recent working group has reported to MBIE on the issues.  There has been an argument put forward to create a separate professional service specifically for contract administration. 

The “closed claims” analysis does not support that proposition.  Only 0.5% of the claims relate to contract administration, and the reality of any claim is that the architect may have done nothing wrong, but was caught in a dispute of others’ making.  The experience of the Claims Committee emphatically indicates that architects perform the role well. 

Overwhelmingly, the perceived contract administration failures are the result of the contractor not providing the necessary information, of the client misunderstanding the role as one of contract management, or they arise out of the observation role.  It is natural for the contractor to assume that the architect cannot be independent as long as they are paid by the client.  Clients often confuse the role of contract management with contract administration, and therefore the architect should take responsibility for the contractor’s performance. 

In smaller projects, or with clients unfamiliar with the process, members should – in their own best interests – take extra effort at an early stage to educate clients on the independence of the contract administration role, and the distinction between contract administration and contract observation. 

The separation of contract administration from contract observation has led to many disputes. NZACS is firmly of the view that – especially for small to medium-scale projects – architects should retain the contract administration role if they are also engaged for contract observation.

BIM Risks

Some members have expressed an interest in understanding the risks associated with BIM – Building Information Modelling.  I don’t claim any particular BIM expertise but the following is drawn from my personal experience on medium to large commercial projects, and is therefore by no means exhaustive.

Before having anything to do with BIM, members should acquaint themselves with the New Zealand BIM Handbook https://www.biminnz.co.nz/nz-bim-handbook and its appendices.

These are very useful documents and contain more detail than the NZCIC guidelines.  More detailed information is also in the international standard ISO 19650.  These documents are a reminder that BIM is much more than a fancy parametric CAD model, and that during the life of a project there are many ways in which ‘information’ might be used.

One of the key aspects of BIM is that the work you do is generally used by and relied upon by numerous downstream parties (e.g. construction, operation) so it’s very important that what you input into a BIM model is correct and so, before you even start, you need good internal modelling standards, templates, and systems.  Also make any limitations about the model/information clear.  A good BIM model is much more valuable than a simple set of drawings and so you should charge appropriately for this.

There are various views of how you can protect your intellectual property rights but, assuming the use of an NZIA AAS, the licence to use the model is similar to the drawings and belongs to them.  The IP also lies in how you model things and carry out Quality Assurance but this will largely remain within your team and not be passed on.

As the lead consultant the architect is often also looked upon to provide BIM Management Services.  Only provide these if you are confident that you have, and can maintain, this skillset.

The following identifies some of the hazard and risk areas by typical workstage.

Project Establishment/Briefing

Request for Proposal (RFP)

  • Dealing with poorly written RFPs.  These can contain broad requirements like ‘a clash-free BIM model is to be provided to the contractor as part of the construction documentation’ or a have requirement to provide ‘a complete as-built BIM model to LOD 300’.  These can be very onerous or impractical, and to manage this risk it is important to review the RFP documents looking for these requirements, seek clarification if possible, and respond clearly with what your proposal includes.
  • If you are part of a consultant team bid then it’s worth doing a pre-contract BIM Execution Plan (BEP) so that everyone knows what they’re committing to and what is covered by the fee.  BIM is typically highly collaborative and such a BEP clearly sets out what everyone is expected to deliver.  This minimizes the risk of disagreements later and, if included in your bid, can make it clear what is in scope.
  • Make sure that you identify and charge accordingly for managing the BIM process if you have that role.  This will include the BIM manager’s time but can also include project related costs like a Common Data Environment (CDE) where the BIM model is hosted, and licences for BIM collaboration and model-checking software.  This can all add up to a considerable sum.
  • Ensure that proper protocols are in place (with all participants) to manage cyber security risks, and make sure you have the appropriate Cyber Liability insurance in place in case something goes wrong.

Briefing

  • It is important to get a BIM brief that is signed off by the client.  The NZ BIM Handbook Appendix E shows an example of such a brief.  On more than one occasion we have had to assist the client with writing the brief.  Confirm that the client understands what they are getting and that you can deliver it.  Getting an agreed brief reduces the risk of the client coming back later with additional information requirements.

Design Stages

The primary risks for this stage of the project are those associated with inefficiencies, poor coordination, and tension with your consultants.

Working with a consultant team during the design stages

  • The foundation for a good consultant team producing good BIM is a well-executed and monitored BEP which is led by the BIM Manager.
  • The BEP makes it clear what is required at each workstage and where responsibility sits, so take the time to properly review and input into this document, and ensure it is agreed upon by all parties as soon as possible.
  • It is important for future users that the project uses OpenBIM (i.e. a non-proprietary format).  Revit is quite dominant with consultants, but ArchiCAD is popular with architects so ensure that consultants are committed to exchanging models in an open formation like IFC (International Foundation Class) rather than their preferred CAD programme.
  • Make sure that your hardware can deal with the large file sizes that you will end up with.  For example, curved pipes and ducts can make these very large.
  • Carry out testing prior to the actual execution of exchanges and clash detection.

The Design Process

  • To have a decent BIM model you should have an internal model-coordinator on your team.  This is different to the BIM manager, which should be regarded as an independent role, even if you are providing those services.
  • Focus on clashes that are appropriate to the workstage.  For example large clashes are important to resolve at early design stages but don’t sweat the small stuff as this will be very time consuming.
  • Be careful of letting the ‘CAD people’ be the only team members engaged in the process.  A successful BIM project needs buy-in from all disciplines and levels, and good transparency to avoid silos developing.

Procurement

The main risks with this project stage are getting tenders/prices that don’t properly take account of the contractor’s BIM responsibilities, and have the potential to generate later claims.

It is very important that tenderers for the construction are aware of the following:

  • The status of the model that they will be provided with, including the level of development of the various BIM Model components.
  • Any limitations or qualifications about the model being provided.
  • What the contractor will be required to do with the model and who will do this work. For example, who will be responsible for updating the model as a result of variations or shop drawings, and what LOD will be required?
  • How will shop drawings be reviewed – drawings only or models only or both?
  • Are as-builts required and what is the level of accuracy of these?
  • Is any BIM reporting needed during the construction phase?

Tenderers should be required to submit a construction BEP to confirm that they properly understand and have included for all BIM aspects.

Construction/Handover/Operation

  • Responsibility during the construction stage will rest largely with the main contractor and sub-contractors.  There may be some risk to the architect if they have a role of updating the model and do this poorly.
  • Like non-BIM projects there is also the obvious risk of variation claims arising from poorly executed design, coordination and documentation in the earlier stages.
  • To enable a smooth handover from contractor to client/user, the defects liability period can be used for a ‘soft landing’.  The BIM Manager is likely to have a role in monitoring this.
  • There are likely to be fewer risks to the design team members during the building operation stage but it’s important to ensure that the client has the necessary skills and software to make proper use of the BIM model.  This will reduce the risk of an operational failure and any possible resultant claim.

Summary

The best way to mitigate BIM risks is the usual combination of good communication, thoroughness, and quality assurance.

You need to think carefully about the fees necessary to do it properly.

Risk management issues

  • The BIM model is dependent on multiple contributors and will be relied upon by others for future unknown decisions.  How do you confine your liability to your input only?  This is likely to require specific terms of engagement. 
  • If an “issue” arises out of the use of the BIM model, there is the potential that you may incur costs and resources regardless of the relevance of your contribution to it.  How do you “ring-fence” or allocate the respective inputs by the various contributors or users?
  • If there is some ambiguity or conflict between the BIM model and the other responsibilities you have under your engagement – or have described in your design/specification – which takes precedence?
  • The definition of quality standards may require amendments to address the standardisation of BIM guidelines.
  • Is there a “BIM protocol” which specifically deals liability and responsibility, order of precedence, and the resolution of conflict?
  • There need to be protocols to trace work carried out in BIM and establish what occurred, who did what to whom and when, and to establish causation in the event a dispute arises.
  • What are the intellectual property rights and ownership issues?  Who “owns” the BIM model and controls access and use?  To what extent does it affect your copyright on design elements?
  • Check that your professional indemnity insurance covers failures due to BIM design, and what additional provisions you may need to make.  Your duty to disclose material facts to your insurer may require you to disclose that BIM is implemented on a project.
  • The operation of BIM on a project may inadvertently allow parties to access information which is otherwise confidential.  Parties may consider restricting access to different areas of BIM.

Observation

Observation

Our website has several articles on  “observation”.  When claims are based on building failures, inevitably the role of observation comes under scrutiny.  This article is the combination of thoughts from four NZACS Directors:  Peter Marshall, Alec Couchman, Michael Davis, and Colin Orchiston.

Observation versus Contract Administration

The current standard forms of engagement and contract intermingle observation with contract administration, and whilst they are interdependent, they are also separate.  This separation of roles is likely to increase, and the NZIA is actively involved in current MBIE consultations around establishing the contract administration role as a stand-alone.

If you are engaged for observation you can report on what you have observed, but the duty to administer the contract – including ruling on variations, certifying payments and completion – rests with the contract administrator. 

A consequence of separating the roles might be that rectification needed as a result of the observation role cannot be enforced because the leverage obtainable by with-holding payments is at the discretion of the separate contract administrator.

The role of Observation by the Architect primarily arises out of the terms of engagement between the Principal and the Architect.  The role of Contract Administration arises out of the (building) contract between the Principal and the Contractor.  If a building contract provides for independent observation (as does NZIA SCC at 8.8 and NZS3910 at 6.4) then those terms will provide the scope and rights/obligations applicable.  If the building contract does not provide for independent contract administration or observation, and/or is inconsistent with the architect’s terms of engagement, the scope and terms will need to be agreed elsewhere, failing which they will be uncertain.

In a larger practice, the roles of designer, contract administrator and observation can be parcelled out to different staff, and the bigger projects suggest repetition of some site activities;  when the same person does all three roles, the familiarity with the project suggests that critical aspects for observation should be known.

Partial Observation is a high-risk option

Any hint that the terms of engagement include observation will lead to assertions that building failures are the result of the architect failing to correct the work at the time it was done. 

This makes the provision of “partial services” or “limited observation” or “site attendance on request only” or some fixed (eg weekly or monthly) site visit frequency a risky proposition which should be resisted.  These arrangements may remove or diminish your control over the sufficiency of your observation, and yet you may still be held responsible for the full weight of “proper” observation. 

It would be nice to just say “don’t do it” but the reality in the market is that it is necessary to view it as an unwelcome option that requires careful risk management. 

  • Who is to say what you could or should have seen when you went on site? 
  • Or whether you were on site sufficiently? 
  • Or for the right reasons or at a critical point in time? 

Our website has several articles on “Partial Services” and they are not the focus of this article, but it is difficult to defend an allegation of inadequate observation on the basis that only “limited” oversight was intended, or was possible.  

One of the early WHRS claims considered the defence offered by a Building Inspector that he was over-worked and the available resources provided by his employer meant that he could not adequately carry out the level of inspection necessary:  unsurprisingly the Court took the view that the regulatory duties were not diminished because of management failures by the provider! 

Against that background, there has to be a very thorough defence to justify why an architect engaged for observation did not – or could not –instruct rectification of observably defective work.

The Observation role should be whole-hearted, with attendances as and when required, with fair and commensurate fees, and with scope and fees sufficiently flexible to deal with changes in the circumstances of the project. 

How much is “enough”?

The Project Architect should assess the level of observation and the frequency of site visits at time of agreeing the terms of engagement.  It is (possibly) more important to set out what you won’t do, than to say what you will do;  and essential to provide for changes to reflect the changing circumstances of the project.  The architect’s risks are compounded if the level of observation as agreed in the original terms of engagement does not correlate with the level of observation later required or sought. 

In smaller projects this may arise because the client removes observation and contract administration from the architect’s scope during the procurement process. 

In larger projects it would not be unusual for the architect to be appointed early in the process and then later a project manager arrives who then appoints and instructs the consultants;  the architect is removed from the contractor procurement process;  contract administration is undertaken by others;  the architect’s role is limited to clarifying the documentation and restricted site access for monthly reporting;  the consultants remain responsible for observation but do not have the power to obtain rectification;  yet on completion the funding agencies look to the architect to certify completion.

Engineers have a structured approach to determining the level of observation and frequency, but it does not take into account the issues we face as architects carrying out observation.  It is not really about how often one visits the site, but whether the site visits capture the critical issues:  that suggests that the project architect should be keeping an eye on the site progress, identifying what issues are likely to be critical if not performed as required, and planning site visits around those issues.  Subject to ongoing review, an initial assessment might be on the following basis:

OL1        Intermittent Site Visits:   small & simple projects                  fortnightly visit

OL2        Periodic Site Visits:           medium complexity & size             weekly visit

OL3        Regular Site Visits:            larger or more complex                 twice weekly visit

OL4        Constant Site Visits:         major complexity and scale          every second day

This may or may not suit the project, the potential risk, or the fee, and is complicated by:

  • Construction activity varying over the duration of the project, from site mobilisation and excavation through to a myriad of trades finishing works.
  • The skills and experience of the contractors and sub-contractors, which may require more observation to mitigate risk.
  • Progress on site varying from programme or expectations.
  • Sufficiency accuracy and reliability of design and as-built documentation, and the level of co-ordination between consultants, may lead to more on-site queries and site visits.
  • Substitutions or redesign sought by contractors;  client and/or project manager changes, demands, expectations;  similarly, from incoming occupants/owners and their funders, and overlaps with fitout requirements.
  • Critical technical and programme issues, specific design complexities, perhaps where the risk of non-compliance varies disproportionally in relation to cost, scale and complexity.
  • The need to exhibit to the contractor and client that you are “on top of things”
  • The number of site visits not reflecting the duration of the visit, eg 1 hour; 3 hours, etc.

There is also a “bell-curve” which is typical:  for smaller projects especially, a lot of attendance is necessary at the start of the job while the builder is grappling with what is required (and the architect is gauging how much hand-holding or vigilance may be required);  in the middle of the project when there is a lot of repetitive work the only reason to visit might be for the purpose of valuing a progress claim;  at the closing stages monitoring of finishing items may be to the level necessary to keep the client happy.

Observation does not mean inspection, or supervision

Lawyers and the courts do not appear to recognize the fine hair-splitting implied in this statement, and lawyers seemingly make no distinction between undertaking one site visit a month as opposed to a permanent site presence when it comes to blame.  But that doesn’t make the distinction incorrect.  It suggests that we need to do more to communicate the distinction. 

Supervision is the control and direction of the work;  Observation is a review of the work done. 

Observation of a typical installation versus every installation

We are judged against what is deemed to be the actions of a reasonable architect in those circumstances at that time.

If you observe a representative quantum of a particular aspect of work to confirm that it matches your documentation and make the assumption on reasonable grounds that the remainder of that work will be similar, those are the actions of a reasonable architect.  If a client wants more than that they need a clerk of works, and even then there’s no guarantee of perfection.

It is reasonable – in absence of evidence to the contrary – that an Architect assume that the contractor is competent:  if a typical item of work is acceptable, and there was nothing to suggest that the remainder of that type of work would be executed any differently, then those other instances of that work may be assumed to also be acceptable.    

But if a window is leaking because of an obvious and observable fault, and the architect did not notice the poor installation when there was the opportunity and need to do so, then they will be dragged into the issue, regardless.  To claim that inspecting one window is sufficient for all windows would be a weak defence if 90% of the windows subsequently leaked (even if the one window the architect did inspect was perfect).  

If you review an item of construction in detail and it is aligned with the documentation and complies with NZBC you can accept it, but you cannot then step back and not carry out observation of those repeating elements.  At the very least you would need to review the repeated elements to the extent necessary to conclude that they were consistent with the item reviewed in detail.  If the review of several such items revealed a variation in installation quality, the conclusion would be that site quality control is lacking, and more follow-up is required. 

The question is whether what was observed was representative of that part of the construction:  inspecting a window “type A” may or may not inform about the installation of types B,C etc.  If there are 100 similar items then a reasonable assessment has to be made whether to observe in detail 1,10, or any number of them to be satisfied that the work is being done as required.  Were they installed by the same persons at a similar point in time?  By skilled or unskilled staff?  What quality controls were in place?  What are the consequences of failure?  Who is likely to respond – and how – in the event of failure?  For marginally acceptable items, how does the installed item compare to independent benchmarks or to supplier’s requirements?

Be very wary of providing any sort of statement as to quality/completion/compliance

Your observation role is to report on whether the work done complies with the contract requirements;  your reporting can only be on the basis of what you have seen, and what you can reasonably infer from what you have seen.  Your reporting will be dependent on the conditions under which the observation took place:  the weather, the available access, whether the item was complete or in progress, and what information was provided to you by those on site who directed the work.  If your reporting is based on assumptions, make those assumptions known. 

Your observation reports will be used for two purposes:  to inform the contract administrator about the progress and compliance with the contract requirements, and to provide ammunition to those who want to pin liability on you for subsequent shortcomings.

Covid or Supply-Chain Costs and Delays

Most of us will be aware of the problems builders are having in getting materials onto sites at reasonable times and costs.  This will have a consequential risk for design practices:  your Risk Management should be looking beyond the short term and thinking about the effect that these problems will have in the future.

If you had any doubt about the seriousness of these issues, take a look here:  https://www.eboss.co.nz/supply-chain-report-2021/background

https://www.corelogic.co.nz/news/construction-costs-rise-22-three-months-june-fastest-quarterly-growth-record#.YTASCo4vNPZ

These issues will impact on client/designer/builder/funder relationships.  The material cost changes of 5% to 25% in the past year or so are the harbinger of more upward movement.  Labour costs are being driven up by tight labour resources and contractors well booked into the future.  The supply chain problems are disrupting site progress, leading to project delays and pressure on contractors’ margins.  

The problems are not ours alone:  America and Europe are also troubled by shortages of materials and labour, slow and expensive shipping and varying lockdown measures.  Covid is driving up inflation generally, and the size of our economy (and construction industry) means we have ineffective leverage on material supplies.

Clients with projects at design stage may be unable to accommodate these costs and delays within their budgets.  Others will continue but with resentment adding stress to the project.  Still others will be looking to continue but with cost cuts which may compromise the design and add to design costs.  Procurement strategies may favour early contractor design involvement, movement away from lump sum contracts to an arrangement which redistributes the risk of delays and cost increases, staged consenting and contracting, and design-stage identification and ordering of items requiring long lead times.

Projects under construction will come under stress if builders cannot complete within the time and cost parameters understood when the project was priced.  If increased costs cannot be recovered, performance on site is at risk or perhaps may be abandoned.  Where costs can be recovered, they will not be welcomed by clients.  Arguments from delays beyond those directly related to Covid lockdowns will be unpleasant.  All of those circumstances represent increased risk to you:  both additional (and perhaps unrecoverable) attendances, and the potential for dispute and negligence claims. In order to manage those risks, please take the time to assess how these issues will affect all the projects you have underway, in particular where reliance has been placed on pre-Covid cost/time estimates, and to communicate appropriately with each client.

Proprietary Systems

Proprietary Systems

Your design includes a proprietary system.  For example a glazed wall or curtain wall system, cladding or a façade cladding system, roof or sandwich panel, a membrane waterproofing system, flashing system – take your pick.  You are reliant on the provider’s information for design documentation (including details specifications and QA systems), on a licensed applicator/installer for the work on site, and on a producer certificate and/or warranty for completion.

When it goes wrong, are you in the cross-hairs?

Apart from being a natural target as the designer holding PI cover, it will depend!

In selecting the product or system for your design, you are entitled to rely on representations by the supplier, but as a professional person it is expected that you at least attempt to divide the facts from the “alternative facts”.  When the blow-torch is applied in the courtroom (several years later), you need to be able to verify that you carried out sufficient enquiry to establish that you made a prudent selection.  And that your selection was made on the basis of the particular circumstances of the project as they were known at the time.

When incorporating the supplier’s information into your design, you still have a duty to assess and make sensible use of their standard detailing to suit the project.  Wind loadings, seismic movement, future maintenance, installation complexity and many other issues will be relevant.  The question is not so much “will it be good enough” but “where, why and how will it potentially fail, and what are the consequences of that?”

The supplier’s information is not usually provided in the form necessary to deal with all the junctions and interfaces with other work;  QA/ fixing details/ lap details/ weathering details may be at odds with your expectations.  Your site-specific design needs to deal with that.  If you “tweak” a standard detail, it becomes your detail, not theirs.  The same if you use a standard detail in a non-standard way.

During the installation, what are your obligations to observe?  You may think that your responsibility is replaced or reduced by using a licensed installer under the supplier’s QA system.  But sooner or later, someone is going to suggest that despite that, you still had a duty to observe and comment on the work.  A licensed installer does not provide certainty of performance;  a supplier’s QA system in turn needs to be assessed and monitored.  At the very least you will have to verify that you reviewed the work to the extent required to be satisfied that the performance requirements and the QA measures were being carried out.

On completion, are you now completely reliant upon documentation by the supplier?  If so, what is in place to make sure you get it when you need it?  Can it be trusted:  it is not unknown for suppliers to sign off on defective work in the hope that it never comes back to bite them.  If the contract requires a warranty, make sure you get it.  But a warranty from a worthless company is worthless!  How hard is it going to be to “collect” on the warranty when required?

And now we are at the point – years later – when the proprietary system and/or building elements in association with it have failed.  Maybe the main contractor, supplier and installer have also “evaporated”.  Worse, close examination reveals that the system was used in a non-standard way, and with substitution of some elements of it, despite the producer statements and warranties.  The performance expectations and technical detailing has become more sophisticated over the years. 

Only now, dear member, do you realise that the fees you earned were inadequate to allow for the careful attention required by the circumstances of this project;  or for the potential future risk that under joint and several liability you (and your insurers) would carry the can for failures by others.

(See also “Reliance on, and co-ordination of trade and consultant advice”)

When contract terms shift the risks and responsibilities

When contract terms shift the risks and responsibilities

The majority of respondents to a 2018 survey by Russell McVeagh lawyers in our industry thought that there had been more disputes over the past two years, and it would get worse in the next two.  That prognosis was more strongly reflected in responses from contractors than from principals.  The survey cited those trends arising out of skill shortages, risk allocation and contract terms.  To that should be added poor communication and lack of comprehension. 

Other recent media reports have highlighted the problems arising when contract terms shift the risks and responsibilities from where they might reasonably fall.  Some government procurement bodies and large developers are doing – at a larger scale – what homeowners often do through a lack of understanding:  assuming that in appointing an architect (or a contractor) they will devolve all risk onto them. 

Stick with NZIA conditions of engagement and contract terms if you can!  It is the NZACS experience that cost savings in consulting fees or truncated services bear an inverse relationship to the potential for later disputes.  Designers are not motivated to provide thorough documentation at punitive fees, and an underpaid contractor is less likely to provide glowing performance.  The designer’s absence from the construction phase seems to result in less documentation (when really it may require more) and contractors are at increased risk if the documentation is not adequate, or is adequate but not understood. 

The principal may assume that contract observation and administration by the designer is a waste of money.  Then, when it proves it was needed, their view is that the design documentation was deficient.  The time to resolve problems is usually as soon as the information is available to do so, but in such cases the contractor is reluctant to call in the designer because that would end up costing him and/or the principal money.  So the problem festers, and probably escalates. 

In the alternative, if the designer is involved in contract administration, the uniformed principal conflates the role with contract management, and the contractor’s defaults become the designer’s failures.

Yes of course NZACS members already know all this!  But what is routine for us is not routine for our clients:  prudent risk management requires us to think about things from their perspective, and to communicate with them in such a way that the designer’s – and the contractor’s – risks and interests are recognised and accommodated.

Completion Statements

Completion Statements

When developer-driven housing projects cut out the architect for observation during the construction phase, it often turns out that they later require a completion statement in order to meet the terms of sale for the units.  This task is fraught with problems:  if you have not been involved in the construction as it happened, how can you possibly offer a sensible opinion on how that work was carried out? 

No matter how carefully you seek to limit your completion statement to “what you can see, when you saw it” the pressure to expand that statement to meet the requirements of individual purchasers will be immense, and the interpretation of it several years later when things have gone wrong is beyond your control.  Even if you were only required to certify in relation to fitness for occupation, inevitably the question will arise about why you did not – at the same time – see something else which (several years later) caused costly problems.

This is an issue that should be dealt with at the time you are engaged for the project, when the proper scope and risk management arrangements can be put in place.  Hopefully the extent and purpose of your attendances during construction is clearly described.  If it is limited in extent, that will be a very important matter to set down.

We have dealt with this many times before!  See, for example under posts for Practical Completion and Fitness for Purpose Statements.

On a similar issue, different clients (and/or their funders) have different ideas about what a statement of practical completion should say.  Again, this is an issue that should be discussed at the beginning (so you can prepare for and charge accordingly) rather than near the end of the project, when you can be leveraged to your disadvantage.  Clients have been known to demand a statement of practical completion – using their text – in return for a prompt payment of long outstanding fee invoices.

You will recognise what comes next:  The short point is:  the NZIA or CCCS terms are “neutral” and built up from many years of experience in projects of all types and sizes, so you should be VERY AFRAID of attempts by others to reinvent the wheel, with the prospect of unexpected and potentially unwelcome outcomes.

You can only “certify” on the basis of the work you have undertaken;  so it would be useful to qualify any statements so as to make it clear that you are only commenting on the basis of (and to the limited extent of) the scope of work for which you were engaged.  And if others have altered what you did in any way (with or without your knowledge), you cannot be responsible for that unless you have specifically accepted the change.

In the absence of a statement limiting your involvement, the chances are that you will be held to have been part of or party to something that may have not been within your control.  For example, if a client changes an item unilaterally or contrary to your advice, you do not want to be later confronted with the assertion that (by default) you agreed to it.

Be aware that if it comes to a claim against you, there is every prospect that any and all of your documents might be available to the claimant, whether you agree or not.  That means that correspondence, site notes and office memos must all be consistent:  in the event of discrepancy or contradictions or ambiguities, the claimant will exploit those against you.

If your statements are reliant on information provided to you, then make that clear.  To some extent you will have a duty to review and accept that information, in other cases you would be wise to accept it without review, but in all cases, you will need to be satisfied that it meets your expectations as a prudent architect.

You should not be making a statement which might suggest your taking responsibility for the actions of others.  By way of example, let’s take the issue of a CCC by the BCA.  It would be a simple statement of fact if you confirmed that a CCC had been issued;  but you would most assuredly be putting the noose around your neck to state that a CCC had been issued “and all compliance requirements have been met”.  If it is later found that the CCC was wrongly issued, your statement will join you into that problem.  It is easy to apply the same principle to all sorts of warranties and producer statements by others, where the issue will be whether the contract requirements (or consultant requirements) have been met.

Similarly, if you have adequately observed the work, you could reasonably state that the contract requirements set out in the documentation provided by you under the terms of your engagement have, to the best of your knowledge and belief, (and if relevant, in reliance on listed documentation by others) been satisfied.  But there is no reason why you should put yourself at risk by saying that the work complies with this or that law or regulation, or that it is fit for purpose and/or meets the expectations of anyone else.