Communique September 2017
On the 3rd August, 2017, the UK Supreme Court delivered its judgment in MT Højgaard v E.ON Climate & Renewables UK Robin Rigg East Ltd [2017] UKSC 59. The case involved a design and build contract for the construction of wind farms. At issue is the balance of “design” responsibility: designer .v. builder.The contract terms incorporated the following:
The foundations failed. On investigation, it was found that if the contractor’s design had followed the employer’s technical requirements, the specified lifespan would not have been achievable.The court said: ‘Where two provisions … impose different or inconsistent standards or requirements, rather than concluding that they are inconsistent, the correct analysis … is that the more rigorous or demanding of the two standards or requirements must prevail, as the less rigorous can properly be treated as a minimum requirement. Further, if there is an inconsistency between a design requirement and the required criteria, it appears to me that … although [the contractor] may have complied with the design requirement, [the contractor] would be liable for the failure to comply with the required criteria, as it was [the contractor’s] duty to identify the need to improve on the design accordingly.’
In this case, the project was a true “design-build” on the basis of minima set by the principal. But an architectural design will always to some extent be an indication of “intent” rather than finite detail: this case will be relevant where a building contractor’s defence relies on inadequate design documentation. It reinforces the point that a builder is still expected to apply common sense and reasonable competence, and to raise a query with the designer where aspects of the design appear defective or at odds with compliance documents or good practice: